FY 2015 ANALYSIS OF DREDGING COSTS
ACTUAL AMOUNTS FOR FY 2015
Total Corps of Engineers
EXPENDITURES FOR DREDGING (Dollars in $000)
CUBIC YARDS DREDGED (CY in 000)
 
FEDERAL
NON-FEDERAL
WORK FOR OTHERS (REIMBURSE)
FEDERAL
NON-FEDERAL
WORK FOR OTHERS (REIMBURSE)
CONTRACT (O&M, CG, MR&T) MAINTENANCE Hopper
$117,689.9
$7,407.5
$26,218.6
26978.7
789.5
1575.1
Non-Hopper
$568,897.8
$17,161.8
$47,483.1
103515.2
651.7
5070.1
NEW WORK Hopper
$62,190.8
$14,333.0
$0.0
2773.5
368.9
0.0
Non-Hopper
$25,125.8
$151,805.9
$0.0
577.6
3646.0
0.0
GOV'T PLANT (O&M, CG, MR&T) MAINTENANCE Hopper
$78,176.9
$1,206.2
$0.0
11086.2
103.0
0.0
Non-Hopper
$54,513.9
$183.0
$3,672.0
13129.5
73.0
2351.0
NEW WORK Hopper
$0.0
$0.0
$0.0
0.0
0.0
0.0
Non-Hopper
$0.0
$0.0
$0.0
0.0
0.0
0.0
HURRICANE SANDY SUPPLEMENTAL WORK CONTRACT Hopper
$176,800.0
$0.0
$0.0
8832.5
0.0
0.0
Non-Hopper
$85,727.1
$0.0
$0.0
3936.1
0.0
0.0
GOV'T PLANT Hopper
$157.5
$0.0
$0.0
14.5
0.0
0.0
Non-Hopper
$2,242.3
$0.0
$0.0
132.8
0.0
0.0
PL-99 WORK (EMERGENCY) CONTRACT Hopper
$0.0
$0.0
N/A
0.0
0.0
N/A
Non-Hopper
$0.0
$0.0
N/A
0.0
0.0
N/A
GOV'T PLANT Hopper
$0.0
$0.0
N/A
0.0
0.0
N/A
Non-Hopper
$0.0
$0.0
N/A
0.0
0.0
N/A
 
   
TOTAL DOLLARS = $1,440,993.1
TOTAL CY = 185,604.9